Longfrie Wastewater Network Extension Project to Start Soon

Guernsey Water would like to remind islanders that the next phase of its wastewater network extension programme will be commencing in the Route du Longfrie area of St Pierre du Bois from 29th September 2014.

The project to extend the public sewer will incorporate a number of roads in the area, and will take approximately 10 months to complete. Once installed, the extended sewer will allow up to 103 properties to connect.

Route du Longfrie Wastewater Project

UPDATE – Completion of this project will now be on 7th August rather than 18th July due to rock. We apologise for any inconvenience this may cause.

Wastewater Network Extension to Start in Route du Longfrie

Guernsey Water is advising islanders that the next phase of its wastewater network extension programme will be commencing in the Route du Longfrie area of St Pierre du Bois from 29th September 2014.

The project to extend the public sewer will incorporate a number of roads in the area, and will take approximately 10 months to complete. Once completed, the extended sewer will allow up to 103 properties to connect.

BACK TO TOP

From Twitter

Earlier today we delivered 1k ltrs of water to Chaos Festival. Have a great weekend and make sure you all keep well… https://t.co/lV6EyfrGPG
If all water vapor in our atmosphere fell as water at once, it would only cover the globe with about an inch of wat… https://t.co/TsqbL0EfPJ
(2/2) as the Guernsey Kart & Motor Club host their reservoir sprint. Off road areas of the walk will remain open.
States of Guernsey Trading Asset