Existing Raw Water Outfall to be Upgraded at Bulwer Avenue

Guernsey Water will shortly be upgrading the Richmond Corner raw water outfall which will require the use of temporary traffic lights along Bulwer Avenue.

The project, which is part of a phased workstream that has already seen the upgrading of the Marais Stream Pumping Station, will commence on 4th October and is expected to take 6 weeks to complete. However, the traffic management arrangements along Bulwer Avenue should only be in place for the first week of the project.

BACK TO TOP

From Twitter

Amazing photo of our St Saviour's reservoir at sunset. Thanks for sharing @stostevin https://t.co/aQmJXRHx2m
3/3 Engineers will be on site if residents have any queries, alternatively Guernsey Water can be contacted on 239500.
2/3 Residents may also notice a slight change in taste as sources swap from Longue Hougue to St Saviours. Residents have been advised.